Planning an install over the shutdown
December shutdowns come around fast, and heavy machinery installations need more than a free weekend to go smoothly. If you want a gantry plasma system running when the plant restarts in January, the groundwork has to start before the shutdown begins.

Start with the foundation calendar
The foundation is usually the first item that can delay the whole programme. Concrete needs the right time to cure, and anchor bolts, grout and level checks all need to be done properly before we bring in the gantry. If the slab is still green when shutdown starts, the machine arrival date does not matter, because installation will sit and wait.
We work backwards from the shutdown window and confirm when civil work must be complete. That gives the client time to pour, cure, test levels and clear any last changes before the rigging crew arrives.
Make crane and access room available
Heavy gantries do not slide into place on their own. Crane access, fork access, lifting points and a clear route into the bay all need to be checked early, especially if the site is busy with end of year stock movement.
- Confirm the lifting capacity needed for each major component
- Clear roof trusses, doors and floor routes before delivery
- Check the bay can accept the machine in one movement, not with repeated rehandling
- Set aside space for packing, tools and assembly staging
Have power and gas ready before handover
Power is not only about switching on the machine. We need the correct supply, safe isolation, earthing and a clean path for control cabling, torch services and extraction support. If the supply is not signed off, commissioning stops while electricians return to finish the job.
Gas readiness matters too, especially where the cutting setup uses oxygen, air or other assisted services. Bottles, manifolds, regulators and pipework should be in place, tested and accessible before the first cut trial.
Book the sign-off steps early
Shutdown time disappears quickly once maintenance teams, contractors and production staff are all trying to finish at once. We recommend putting sign-off tasks on the calendar before the break, so there is no confusion over who approves what on site.
That includes civil sign-off, electrical sign-off, safety checks, machine alignment, test cuts and operator handover. If each step has a named owner, the team can move through commissioning without losing days to waiting around.
What we need from the site team
To keep a December installation on track, we ask for a few practical things from the client side. The more of this that is ready before the shutdown, the smoother the January restart will be.
- Confirmed foundation drawings and finished slab dates
- Access for delivery vehicles and lifting equipment
- Power supply details and electrician availability
- Gas and consumable storage space
- A clear sign-off contact for the site
Questions we get asked
How early should we plan a December gantry installation?
As early as possible, ideally before the first week of December. Foundation work, power checks and crane booking usually take longer than people expect, especially when year-end shutdown dates move around.
Can we pour the foundation during the shutdown and install straight after?
Usually not. The concrete needs enough cure time to reach a safe, stable condition before heavy equipment is anchored and aligned. We confirm the slab timing before we book the installation window.
What is the biggest cause of delay on shutdown installs?
The most common delays are incomplete foundations, late crane access, and power or gas readiness not being finished in time. A clear sign-off plan helps prevent all three.